The former minister of Ministry of Communications, Mr. Huangzhengdong inspected the water area pf Gangwei in Longhai in Zhangzhou (now China Merchants Zhangzhou Development Zone), then put forward the developing assumption.
September 10 th ,1991
The former nomarch of Fujian , Mr.Jiaqinglin inspected the water area vicinal to Gangwei in Longhai, Zhangzhou.
December 28 th ,1992
China Merchants Zhongyin Zhangahou Economy Development Zone laid foundation at Nanpaotai (Yuzaiwei village in Gangwei, longhai, Zhangahou), put forward the development strategy of prospering the Zone depending on port. In order to advance the fame of the port, it is called “ Zhangzhou Port ”.
June 28 th ,1993
The DWT35000 berth of Zhangzhou Port (Berth No.3) began to construct.
November 3 rd ,1994
Zhangzhou City Government approved to set up the administrative organization of Berth No.3-Zhangzhou Port Authorities.
August 21 st , 1996
The Ministry of Communications approved the Zhaoyin Harbor district ( Zhangzhou Port ) to be one of the first trial ports with direct sails to Taiwan .
July 8 th ,1999
The construction of the principle part of Berth No. 4 to No.5 began and the ribbon was cut at the opening ceremony.
July, 13 th ,2000
China Merchants Zhangzhou Development Co. , Ltd. and China Merchants Holdings (international) Company Limited signed the letter of intent to manage Berth No.3 by joint venture (the latter undertakes all the management affairs).
September 30 th , 2000
The joint venture --- Zhangzhou China merchants Port Co., Ltd. was registered to be founded. The reward system was reformed roundly and the development of Zhangzhou Port was reorientation.
January 8 th ,2001
The first domestic trade container line was developed and broke the history of no container line in Zhangzhou Port.
June 3 rd ,2001
The mineral building material terminal (Berth No.14) of 10000 DWT began to construct and finished on December 29 th , 2001
December 30 th ,2001
The principle part of Berth No.4 and No.5 was finished and simply equipped to put into production.
January 1 st ,2002
Zhangzhou Port (Zhaoyin harbor district) where Zhangzhou China Merchants Port is located was formally open to the ships of foreign registry.
February 7 th ,2002
The principle part of Berth No.4 to No.5 was finished and appraised to be a fine engineering by the quality inspection station of Fujian Province after its inspection and check.
August 20 th ,2002
The yard of 61000 square meter behind Harbor Building began to construct.
September, 9 th ,2002
The warehousing center began to construct and a ribbon was cut at the opening ceremony.
March 13 th ,2003
The yard of 61000 square meters behind Berth No.3 was finished and accepted.
January 7 th ,2004
The steel structure of the first silo in warehousing centre began to install.
February 28 th ,2004
The principle part of Berth No.1 and No.2 with quay line of 488 meter began to construct.
June 1 st , 2004
The warehousing center formally was put into use.
June 20 th ,2004
The northern four lanes of the gate of Berth No.1-6 were put into use.
October 16 th , 2004
Ministry of Commerce of the people's republic of China agreed that the total investment of Zhangzhou China Merchants Port Co., Ltd. was added from 0.8billion to 1.8 billion and the registered capital was added to 1 billion from 0.66 billion (file No.: Commerce Capital Approval [2004] 1608).
December, 25 th , 2004
Berth No.7, No.8 and No.9 began to construct and held opening ceremony on December 28th.